Power supply to half of the country restored after more than four hours suspension due to grid failure which occurred at around 11:20am Tuesday.

Iswardi-Ghorashal and Ashuganj-Sirajganj power transmission lines restored at around 3:00pm, Power Grid Company of Bangladesh managing director Masum-Al-Beruni confirmed New Age.

He said that power supply situation had become normal in Rangpur, Rajshahi, Khulna and Barisal divisions.

At first Iswardi-Ghorashal transmission line went out of order as a tower affected by nor’easter at around 9:00pm Monday, said officials.

The second transmission line, Ashuganj-Sirajganj line, tripped before restoration of the Iswardi-Ghorashal line leading to stop power supply in the four divisions as well as to shut down some 24 power plants in the divisions, they said.

 